Once the connections are all secure, turn on the power (switch is located externally on the upper left side of the
cabinet on the control panel). The initial start-up will require up to 1 hour to fully pressurize the internal storage tank
to the correct level. External pressure gauge (at the top coming off the 4
th
port from the left) can be viewed to verify
that the internal storage tank has been filled to 65-75 psig. Once the tank is full, the system will automatically go
into a standby mode and is ready for standard operation.