BeerBlast™ 7/14KPH & N2-GEN™ 7/14KPH O&M South-Tek Systems
21
Once the connections are all secure, turn on the power (switch is located externally on the upper left side of the
cabinet on the control panel). The initial start-up will require up to 1 hour to fully pressurize the internal storage tank
to the correct level. External pressure gauge (at the top coming off the 4
th
port from the left) can be viewed to verify
that the internal storage tank has been filled to 65-75 psig. Once the tank is full, the system will automatically go
into a standby mode and is ready for standard operation.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the South-Tek Systems BEERBLAST 7 KPH and is the answer not in the manual?

South-Tek Systems BEERBLAST 7 KPH Specifications

General IconGeneral
BrandSouth-Tek Systems
ModelBEERBLAST 7 KPH
CategoryInverter
LanguageEnglish

Related product manuals