INSTALLATION
Commissioning
82 | DHE www.stiebel-eltron.com
Changing the connected load via jumper slot; only with
DHE18/21/24
If you select a connected load other than the 21kW factory setting
for appliances with selectable connected load, you will need to
reposition the jumper.
1
2
3
D0000089187
Install the jumper in the required position on the pin strip.
Jumper position Connected load
1 18kW
2 21kW
3 24kW
No jumper 18kW
11.2 Initial start-up
≥ 60 s
D0000053277
Open and close all connected draw-off valves several times,
until all air has been purged from the pipework and the
appliance.
Carry out a tightness check.
D0000053278
Activate the safety switch by firmly pressing the reset button
(the appliance is delivered with the safety switch disabled).