Models C706 & C707
Introduction
Installation o f Syrup Rail (X48015--27)
The syrup rail can be mounted to either the left or right
side of the C706 or C707 units regardless of whether
the top air discharge chute is used. The syrup rail can
mount to only the left side of the C708 or C709 if the
top air discharge chute is not used. If a top air
discharge chute is used with the C708/C709, then the
syrup rail can be mounted to either side.
Perform the following steps to mount the syrup
rail on the side of a unit where a top air discharge
chute is not installed:
1. Remove the (4) panel screws as shown in
Figure 4.
Figure 4
2. Install the Mounting Assembly Syrup Rail
(X57317) using the (4) Spacers (053600) and
the (4) Screws--1/4--20X3 HEX CAP (025984)
with (4) Washers (000655).
3. Install the (4) Plugs Square Tubing (057381)
in the ends of the Mounting Assembly Syrup
Rail (X57317).
4. Install the (3) Holding Collars (046551) using
the (3) Screws--10--32X3/4 OVAL HD--SS.
5. Hang the Syrup Rail Assembly (048015--27) on
the holding collars.
Perform the following steps to mount the syrup
rail on the side of a unit where a top air discharge
chute is installed:
1. Three holes must be created in the side of the
chute as in the Figure 5.
Figure 5
2. Install the (3) Nutserts (021106) in the panel.
3. Install the (3) Holding Collars (046551) using
the (3) Screws--10--32X3/4 OVAL HD--SS
4. Hang the Syrup Rail Assembly (048015--27) on
the holding collars.