10.1 SAFETY PRECAUTIONS DURING MAINTENANCE WORK:
▪ Shut down the wind turbine system (section 8.2).
10.2 INSPECTION AND MAINTENANCE SCHEDULE:
Check for abnormal noises
Check that the blades turn freely
Yearly twice / at
end of winter or
after extreme
weather events
Inspect for cracks / damage and if necessary, replace
Treat with underbody protection wax
Are the rotor blades balanced?
Is the Base mounted properly?
Inspect the cables for damage
INSPECTION SCHEDULE TABLE
▪ Refer to the supplementary documents for information on maintaining supplier
components.
WARNING: Risk of injury when carrying out maintenance work! X Shut
down the wind turbine system prior to all maintenance work. X Take steps
to prevent the wind turbine system from being switched on again by
unauthorised persons.
WARNING: Shut down the wind turbine system immediately if the rotor blades or
the electrical wiring are damaged.