– 254 –
<Installing compressor>
Install a compressor by following the dismantling procedure in reverse.
The dismantling process may have loosened compressor leads and faston connectors. Prior to installation,
therefore, tighten them a little with a pair of pliers, and verify that they are tight after reconnection.
Notes:
The tightening torque of the hexagonal bolts, used to mount the compressor, is 200kg·cm.
<Vacuum-pumping>
(Single outdoor unit system)
Before performing vacuum-pumping, fully open PMV1, 2 and 4. If they are closed, the heat exchangers of the
outdoor unit cannot be vacuum-pumped.
Connect a vacuum pump consecutively to the check joints placed in the liquid and discharge pipes and on the
high-pressure side of the suction pipe, and turn it on.
Operate the vacuum drying until the vacuum gauge indicates 1 mmHg.
<Method to fully open PMV manually>
(1) Turn on the power switch of the outdoor unit.
(2) With the Bits 1 and 2 of SW12 set to off, short-circuit the pins of CN30.
(3) Disconnect the connectors of PMV1 and 2 from the I/F P.C. board.
(4) With the Bits 1 and 2 of SW12 set to off and on, respectively, short-circuit the pins of CN30.
(5) Disconnect the connector of PMV4 from the I/F P.C. board
(6) Turn off the power switch of the outdoor unit.
Note: Steps (4) and (5) are not required for MMY-MAP0804, 1004 and 1204
<Refrigerant charging>
Inject the same amount of refrigerant as the recovered residual refrigerant via the charging port of
the liquid-side service valve.