EasyManua.ls Logo

Trane RTXC XE Series - Page 3

Trane RTXC XE Series
56 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
3
Installation Completion and Request for Trane Service
Important: A copy of this completed form must be submitted to the Trane Service Agency that will be responsible
for the start-up of the equipment. Start-up will NOT proceed unless applicable items listed in this form have been
satisfactorily completed.
TO:
TRANE SERVICE OFFICE:
S.O. NUMBER:
SERIAL NUMBERS:
JOB/PROJECT NAME:
ADDRESS:
The following items are being installed and will be completed by:
Important: Start-up must be performed by Trane or an agent of Trane specifically authorized to perform start-up
and warranty of Trane® products. Contractor shall provide Trane (or an agent of Trane specifically authorized to
perform start-up) with notice of the scheduled start-up at least two weeks prior to the scheduled start-up.
Equipment not started by Trane is not warranted by Trane.
Check box if the task is complete or if the answer is “yes”.
Unit location
Provide enough space around unit to allow unobstracted air flow
Unit mounting placed on a rigid and level foundation
Isolator installed and fully tightened
Secure no external vibration transmited to the unit
Provide enough space around unit for installation and service personnel unrestricted access
Wiring
Wiring size per all national or local codes and equipped with the remote fused disconnect switches
Inspect all wiring connections to ensure correct and tight
Ground all customer supplied power wires as required by applicable codes
Distance between low voltage line and power wiring meet required
Check compressor wiring connections corrected and tightened before power on
Provide separately power for anti-freeze heater of evaporator, PHR BPHE or water pipes
Piping
Water system designed by professional designers, such as piping diameter etc.
Water pump head pressure matches actual water side Resistance
Water strainer installed before inlet of the unit and cleaned prior to connection
Water pressure guages installed with shutoff valves to monitor evaporator pressure drop
Vibration eliminators equipped to prevent vibration transmission through the water pipes
Air vent, drain and feed valve at the right position of water system
Meet minimum water loop volume of 9 liter/kW to stable leaving water temperature for comfort
cooling
Thoroughly flush all external water piping before final piping connecting to the unit
Pass water system pressurization test and no water leakage identified
Water system filled and air bled from system
Anti-freeze protection actived after water system filled in winter
Flow switch installed (if not factory-provided)
External interlocks (flow switch, pumps auxiliary, etc.) per Wiring Schematics of the manual
Water piping insulated and fixed
Evaporator bypass valve installed as required (if installed)
Installation Completion and Request for Trane Service
Power Supply
Voltage must be within the utilization range of the unit nameplate and imbalance must not exceed
2%
Power supply should not be temporarily provided
Power phase sequence correct
Owner or representative should participate the commissioning
Enough equipment support, like ladder, elevating platforms, etc. for the commissioning personnel
Oil sump heaters operated at least 12 hours before starting
Measure and check the oil sump level within allowable range before startup (if necessary)
Test
Dry nitrogen available for pressure testing (if necessary)
Refrigerant
Refrigerant on job site and in close proximity to unit (if shipped separately)
Note: After commissioning is complete, it is the installer’s responsibility to transport empty refrigerant
containers to an easily accessible point of loading to facilitate container return or recycling.

Related product manuals