Installation
24 RT-SVX23F-EN
3. Position SUPPLY DUCT COVER as shown, rotate 90
degrees to allow entrance into supply opening.
4. Slide SUPPLY DUCT COVER into duct openings until
inward edge of duct cover engages with the 2 retaining
clips on the duct flanges. Secure the outward edge of
each duct cover with 2 screws.
5. Slide RETURN DUCT COVER (insulation side up) into
supply opening until inward edge of duct cover
engages with the 2 retaining clips on the duct flange.
Secure out-ward edge of the duct cover with two
screws.
Note: Certain unit/electric heater combinations require a
limit switch change out for horizontal airflow
applications. Refer to the following instructions to
determine if this process is required for the unit
undergoing installation.
6. After completing installation of the duct covers for
horizontal discharge, proceed toTCO-1 instructions.
Horizontal Discharge Conversion WSC060-
120E (5 - 10 Ton Units)
Note: 5 - 10 ton units supply cover to return opening and
return cover to supply opening.
Supplies needed by installer for conversion: 3 oz. tube
of highTemperature RTV sealant. (500°F/260°C:
Similar to Dow Corning 736)
Important: Failure to use recommended sealant could
result in unit performance loss.
If a unit is to be converted to a Horizontal discharge, the
following conversion must be performed:
1. Remove RETURN and SUPPLY duct covers.
2. Place SUPPLY DUCT COVER over downflow return
opening. (insulation side down)
3. Using self-drilling screws, (or screws removed from
duct cover), screw through dimples to attach Duct
Cover to base.
4. On original RETURN DUCT COVER, apply ¼” (6mm.)
continuous bead of 500°F RTV sealant around flange
(opposite insulation side), as shown.
5. Slide RETURN DUCT COVER (insulation side up) into
supply opening until inward edge of duct cover
engages with the 2 retaining clips on the duct flange.
Secure outward edge of the duct cover with two
screws.
Figure 24. Supply duct cover
Figure 25. Supply & return openings
RTV Sealant
Supply duct cover with
RTV installed
Figure 26. Supply duct cover
Figure 27. Return duct cover
Figure 28. Supply & return openings
Supply Duct Cover
Screw into 4
dimples on top
edge
RTV Sealant
Insulation side
down
Supply duct cover
Insulation side up
Return duct
cover