Vertiv I Liebert Air Cooled Condenser I User Manual 7
Chapter 2 Installation
This chapter introduces the moving, unpacking, inspection, installation notes, space
requirements and installation procedures.
2.1 Moving, Unpacking And Inspection
Moving
It is recommended to use the mechanical transport equipment such as a forklift or a crane
when unloading and transferring the condenser closest to the installation site.
When a forklift is used, insert the tines of the forklift shown in Figure 2-1 (taking the single fan
condenser for example).
Forklift
direction
Figure 2-1 Forklift direction
When a crane is used, refer to Figure 2-2 to lift the package (taking the double fans condenser
for example).
When lifting the package, fix the cable by leading it through the slots located at the
bottom of the pallet. Otherwise, the cable may slide during the lifting process, and
the package may fall to the ground, damaging the pipes inside and resulting in
system leakage.