5) FINAL TESTING
Skilled staff authorised by VIMEC must test the lift system.
Run the lift up and down a few times, checking that:
- There is no interference between the platform and the shaft.
- There are no unusual vibrations or strange noises.
- The platform stops in exactly the correct positions at the oors.
- Static tests
- Static load of 1.25 times the maximum load
(500 kg) midway through the lift travel (lift stationary).
- Check operation of the lift without load.
- Dynamic tests
- Operate the lift with 1.1 times the maximum load (440 kg).
- Check the lift functions and safety functions.
- Check operation of the controls.
- Check operation of the emergency Stop.
- Check operation of the emergency raising/lower¬ing system.
- Check operation of the alarm system.
- Insulation test (see folder of wiring diagrams).
- Following the diagram provided in the electrical wiring diagram folder.
6) OPERATING CHECKS AND ADJUSTMENTS
- Run the lift up and down several times, checking that the electrical and mechanical parts and safety devices are
operating correctly.
- Check that no sheaths or obstacles are interfering with moving parts.
- Adjust the oor sensors so that the platform stops exactly level with the oor threshold (See folder of wiring
diagrams).
- Check that all the metal fasteners have been securely tightened.
- Check that the doors are only released within a range of ± 50 mm in relation to the threshold of the corresponding
oor.