Benchmark Platinum-Edge [II]: Operation-Service Manual
SECTION 8 MAINTENANCE
OMM-0137_E • GF-211 12/13/2019 Technical Support (800) 526-0288 • Mon-Fri, 8 am - 5 pm EST Page 121 of 153
8.12 RETURNING THE BOILER TO SERVICE AFTER SHUTDOWN
After a prolonged shutdown (one year or more), the following procedures must be followed:
Placing the Boiler Back In Service After A Prolonged Shutdown Instructions
1. Review installation requirements included in Section 2 of the Benchmark Platinum-Edge:
INSTALLATION Manual (GF-210).
2. Inspect all piping and connections to the unit.
3. Inspect exhaust vent and air inlet duct work (if applicable).
4. Perform initial startup per Section 4 of this guide.
5. Perform the instructions in Section 5: Safety Device Testing, above, and all scheduled
procedures described Section 8: Maintenance.