CNC210 Operating Manual
Covers an area including the machine tool itself covers an area of operation (see figure
below).
4.4.2 Temporary level adjustment
A:Lift or fork the machine, adjusting the pad iron bolts penetrated into the base of the anchor
bolt hole. Then the machine slowly down, and ensure uniform contact.
B:adjusting bolt,for coarse level of the machine.
4.5 Inspection of internal device connection
After finish adjust the temporary level of the machine, the mechanical and electrical system
of the machine shall be checked in accordance with the following provisions.
A:Cleaning. To rust, machine sliding surface and some pieces of metal surface has been
coated on the a layer of anti rust oil,they may pollution by the transport process. anti rust oil must
be clean before use, otherwise there is the danger of damage to the sliding surface. Clean cloth
dipped in oil cleaning, after cleaning we should lubricating the machine in accordance with the
requirements of lubrication.
B:Machine check.Check the machine parts if there have damaged, missing parts or
accessories, whether lubrication is good, hydraulic pipeline whether reliable connection.
C:Electrical system inspection should be carried out before the electrical connection is
switched on
D:After the machine is shut down for a long time, the lubricating system must be started to
make full lubrication.
4.7 The final adjust of the machine.
Re-adjusting the machine in the longitudinal and transverse,the adjust step and allow poor,
please refer to the attached to each machine accuracy test. With the scale of the level meter is
0.02mm.
4.8 Maintenance of initial installation
After the installation of the initial stage, due to the change of base and foundation of the
unstable because of factors, the level of machine will have obvious change, may greatly influence
the machine precision. On the other hand machine initial wear, as well as by the machine
pollution .Extremely easily cause changes in the performance of the machine . So, please
according to the following method for initial and maintenance:
A:Test: after the installation of machine ,the initial test should be very cautious. Test time is
about 1 hours, during the whole test period shall not be heavy load cutting and machining parts.
B:Check at the initial stage of the bed level: from machine installation date six months
should check the bed level, if found any abnormal phenomenon, should be promptly corrected, to
ensure that the requirements of the bed level accuracy is achieved.