INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH
8-716-106-256a (08.05)
10
WATER SYSTEMS & PIPEWORK
WATER SYSTEMS & PIPEWORK
FILLING PRIMARY SEALED SYSTEMS:
Filling the system must comply with one of the
methods shown opposite.
The filling point must be at low level and must
never be a permanent direct fixing to the mains
water supply.
Filling loops must be WRAS approved.
Heating return
Hose
return
Non return
valve
Non return
valve
Test cock
Stop
cock
Water main
supply
Stop
cock
Temporary hose
Heating return
Auto air
vent
Non return
valve
Stop
cock
Make up
vessel
1000mm above
the highest point
of the system

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Worcester GREENSTAR UTILITY and is the answer not in the manual?

Worcester GREENSTAR UTILITY Specifications

General IconGeneral
ModelGREENSTAR UTILITY
CategoryBoiler
Fuel TypeNatural Gas
MountingFloor Standing
Boiler TypeRegular
Warranty2 years

Related product manuals