VESDA by Xtralis VESDA Pipe Network Installation Guide
www.xtralis.com 31
6 Recording Pipe Network Details
Once you have finished installing the pipe network you will need to update the design documents with any
modifications. It is critical that you record any changes from the original plan for the commissioning and
testing phases at the site.
If significant changes to the original plan were required you should retest the new proposed pipe network
before installing it. Failure to retest the design with ASPIRE may lead to the installation of a pipe network that
does not meet customer and local fire authority codes and standards.
After updating the design documents you must give a copy to the person who will be commissioning the
system. The details of the person who will be commissioning can usually be found in the ASPIRE Installation
Data Pack (IDP).