EasyManuals Logo

Yazaki WFC-SC Series User Manual

Default Icon
21 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #4 background imageLoading...
Page #4 background image
WFC- SC(H) Series .Installation
- 3 -
2. Handling
2.1 Rigging
Remove the crate and wooden base from
the absorption chiller-heater. Lift the
machine using a wire rope and eye-bolts
(eye bolts provided with the chiller-heater
as illustrated in figure 1). The dry weight
and overall dimensions are detailed in
section 1 Specifications of this manual.
Care should be taken throughout to avoid
damage to panels and piping connections –
always lift in a vertical manner.
Figure 1
2.2 Access Clearances
Properly plan to ensure an accessible
route to the place of installation before
moving the chiller-heater. If it is not
possible to use a crane for lifting, a
fork lift truck may be utilized. In the
event a crane or forklift cannot be used
and the machine must be manhandled
into position, minimum dimensions for
maneuver are shown in Figure 2
figure 2.
Access Clearance Table (mm)
Dimension WFC-SC10
WFC-SH10
WFC-SC20
WFC-SH20
WFC-SC30
WFC-SH30
WFC-SC50
A
2,365 2,490 2,565
B 1,600 1,905 2,235
2,145
C 1,600 1,905 2,235
2,420
D 1,600 1,905 2,235
2,420
3. Place of Installation
3.1 Location
The Yazaki absorption chiller-heater units have a weatherproof cabinet suitable for
indoor or outdoor installation. Select the location for the chiller-heater with due
consideration to the position and proximity of the cooling tower, and air handling
equipment. Particular attention must be paid to accessing the absorption machine for

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Yazaki WFC-SC Series and is the answer not in the manual?

Yazaki WFC-SC Series Specifications

General IconGeneral
BrandYazaki
ModelWFC-SC Series
CategoryChiller
LanguageEnglish

Related product manuals