PART 3 — EXECUTION
3.01 INSTALLATION
A. General: Rig and Install in full accordance with
Manufacturer’s requirements, Project drawings, and
Contract documents.
B. Location: Locate chiller as indicated on drawings, in-
cluding cleaning and service maintenance clearance
per Manufacturer instructions. Adjust and level chiller
on support structure.
C. Components: Installing Contractor shall provide and
install all auxiliary devices and accessories for fully
operational chiller.
D. Electrical: Coordinate electrical requirements and
connections for all power feeds with Electrical Con-
tractor (Division 16).
E. Controls: Coordinate all control requirements and
connections with Controls Contractor.
F. Finish: Installing Contractor shall paint damaged and
abraded factory nish with touch-up paint matching
factory nish.