Chapter2Pre-InstallationPreparation
Process
Basedonthecontractcongurationrequirements,checkwhethertheuplinkoptical
interfaceorelectricalinterfaceareavailable,whethertheuplinkdevicesareready,
whethertheopticalbersareprepared,andwhethertheopticalberconnectorsmatch.
Conductthefollowinginspectionbasedonthecontractrequirements:
lCheckwhetherthepowercablesforexternalpowersuppliesandcabinetsareready.
lCheckwhethertheODF,DDF,andMDFhavebeenconstructed.
lCheckwhethertheopticalbersarepreparedandwhethertheopticalberconnectors
match.
2.5Unpacking
Thistopicincludesthefollowing:
lUnpackingCabinet
lUnpackingShelf
lUnpackingCard
Note:
Onlythesystemlevelpackagingwillbeprovided.Thecomponentorcircuitpackpackaging
isunavailable.
2.5.1UnpackingCabinet
Performthisproceduretounpackandcheckcabinet.
Prerequisite
Beforeunpackingthecabinet,makesurethat:
lThepackingboxisintact.
lThecabinettypeiscorrect.
Context
Tounpackandcheckthecabinet,performthefollowingsteps:
Steps
1.Countthetotalnumberofthegoods.
Beforeunpacking,itisnecessarytocountthenumberofthegoodsaccordingtothe
packinglistattachedtothepackingboxes.Itisrecommendedtokeeparecordof
goods.