6.6 Draining the gas outlet casing
If there is a boiler leak into the exhaust gas pipe or an ingress of water due to other causes,
the gas outlet casing can be drained.
Fig.20: Drain pipe diagram
01 Drain pipe A Position 1
02 Drain cock B Position 2
03 Drain
04 Air line from compressor casing
u On the drain pipe(01), set the drain cock(02) to position1(A).
If the drain pipe(01) is blocked:
u Set the drain cock(02) to position2(B) and clean the drain pipe(01) with air from the
compressor casing(04).
If cleaning with air is not sufficient, the drain pipe(01) must be cleaned mechanically.