Section 4 Commissioning of PROFIBUS equipment Special conditions regarding the installation of
3BDS009029R5001 B 97
equipotential bonding line must be laid, if possible, in parallel to the data line
(e.g.: 16 mm²). Under no circumstances, the line shield must be used as
compensating line.
Laying of the PROFIBUS cable in separate grid ducts to energy lines. If bus
cables and energy lines are laid in parallel, a minimum distance of 30 cm is
provided.
The lines provided for the energy line (e.g. for converter actuators) are screened
with a copper braiding. PROFIBUS International (PI) stipulates that the bus
cable has additionally to be laid in a steel tube or in a tight sheet metal channel
in case of extreme interference influencing. The tube or the channel must be
earthed regularly and protected against corrosion (see also PROFIBUS
installation Guideline).
The grounding of field cable screens for wiring remote I/O housings with the
field devices must be carried out in conformity with the requirements of the
remote I/O suppliers.