ACS 300 User’s Manual 37
Chapter 5 - Start-up
Flowchart Commissioning
Checklist
SAFETY
•Read and follow the safety instructions on page iii.
INSTALLATION
• Check for proper earthing.
• Check supply and motor cables.
• Check Star/Delta connection.
• Check control cables.
•Check and complete the parameter values.
PARAMETERS
TEST RUNS
•Check the operation of the ACS 300 without motor.
•Check the operation of the ACS 300 with motor connected.
•Check external controls and emergency stop.
•Check the rotation direction.