Installation and commissioning guide
1ZSC000563-ACF EN, REV. A, 2020-06-25
41
8. Tighten the draw-rod nut (10).
G005062
Torque
10 Nm
9.
Remove the bolts (6), washers (7) and lifting
tool (1).
G001935
10.
Remove the pull-through cord (12).
11.
Tighten the draw-rod nut, refer to Hydraulic tightening of the draw-rod nut, page 42, or Manual
tightening of the draw-rod nut, page 45.
End of instruction