Installation and commissioning guide
1ZSC000563-ACF EN, REV. A, 2020-06-25
21
4.4 Installation with draw lead
4.4.1 Installation with draw lead
Overview
G002945
2 Draw lead
12 Pull-through cord
32 Inner terminal
33 Bushing
Procedure
1. Braze the draw lead (2) from the transformer
windings to the inner terminal (32).