Installation and commissioning guide
1ZSC000563-ACF EN, REV. A, 2020-06-25
35
9. Remove the bolts (6), the washers (7) and the
lifting tool (1).
G001935
10.
Tighten the draw-rod nut, refer to Hydraulic tightening of the draw-rod nut, page 42, or Manual
tightening of the draw-rod nut, page 45.
End of instruction
4.6 Installation with draw rod at site
4.6.1 Preparations at site
Overview
This procedure is only applicable if the lower draw rod with the bottom contact (36) is installed in the
transformer.
G006891