A CB condition CBREADY of a type, OCO shall be high (true) before and during
tripping (start auto reclosing). During tripping it goes low for a rechar
ging time, for
example, 10s. It may thus be low at the instant of reclosing. After each Open or
Close operation it may need a recharging period before it goes high again.
In the example of CB simulation arrangement, the CBREADY condition is
simulated by a manual switch, SRY.
Information and material for the verification:
Protection or control unit, IED, configured and with settings entered.
Configuration diagram for the IED
Terminal diagram for the IED, or plant circuit diagram including the IED
Technical reference manual for the IED
IED test set for secondary injection
Means to indicate, measure and record operation and times, for example an
event recording facility
A bi-stable relay (BR) or two auxiliary relays to simulate a CB
Two push-buttons (SC, ST) to operate the BR and a change-over switch (SRY)
to simulate CBREADY
Possibly a switch simulation the synchronizing check SESRSYN condition
IED
CLOSECB
Trip
CBCLOSED
CBREADY
BR
SC
ST
SRY
To test
set
+ -
IEC04000202-3-en.vsd
IEC04000202 V3 EN-US
Figure 53: Simulating the CB operation by a bi-stable relay/breaker simulator
and manual switches
1MRK 505 378-UEN A Section 11
Testing functionality by secondary injection
Line differential protection RED670 2.2 IEC 231