EasyManuals Logo

ABB RED670 User Manual

ABB RED670
308 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #265 background imageLoading...
Page #265 background image
phase fault between two other phases within the time interval, shorter
thantEvolvingFault (default setting 2.0s).
Check, that the output signals, issued for the first fault, correspond to a two-
trip for included phases. The output signals generated by the second fault
must correspond to the three-phase tripping action.
11.12.1.4 Circuit breaker lockout
SEMOD54375-170 v11
The following tests should be carried out when the built-in lockout function is used
in addition to possible other tests, which depends on the complete configuration of
an IED.
1.
Check that AutoLock and TripLockout are both set to Off.
2. Activate shortly the set lockout (SETLKOUT) signal in the IED.
3. Check that the circuit breaker lockout (CLLKOUT) signal is set.
4. Activate shortly thereafter, the reset lockout (RSTLKOUT) signal in the IED.
5. Check that the circuit breaker lockout (CLLKOUT) signal is reset.
6. Initiate a three-phase fault.
A three-phase trip should occur and all trip outputs TRL1, TRL2, TRL3
should be activated. Functional outputs TRIP and TR3P should be active at
each fault. The output CLLKOUT should not be set.
7. Activate the automatic lockout function, set AutoLock = On and repeat.
Besides the TRIP outputs, CLLKOUT should be set.
8. Reset the lockout signal by activating the reset lockout (RSTLKOUT) signal.
9. Activate the trip signal lockout function, set TripLockout = On and repeat.
All trip outputs (TRL1, TRL2, TRL3) and functional outputs TRIP and TR3P
must be active and stay active after each fault, CLLKOUT should be set.
10. Reset the lockout.
All functional outputs should reset.
11. Deactivate the trip signal lockout function, set TripLockout = Off and the
automatic lockout function, set AutoLock = Off.
11.12.1.5 Completing the test
SEMOD54375-203 v6
Continue to test another function or end the test by changing the TESTMODE
setting to Off. Restore connections and settings to their original values, if they were
changed for testing purposes.
11.13 Monitoring
SEMOD53581-1 v1
11.13.1 Gas medium supervision SSIMG
GUID-0A83B4D5-51FF-43CB-8DC7-AFCEA2BC7B69 v2
Prepare the IED for verification of settings as outlined in Section
"Preparing the
IED to verify settings" in this chapter.
1MRK 505 378-UEN A Section 11
Testing functionality by secondary injection
Line differential protection RED670 2.2 IEC 259
Commissioning manual

Table of Contents

Other manuals for ABB RED670

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB RED670 and is the answer not in the manual?

ABB RED670 Specifications

General IconGeneral
Rated Frequency50/60 Hz
Product TypeProtection Relay
Rated Voltage100-240 V AC/DC
Communication ProtocolsIEC 61850, IEC 60870-5-103, DNP3
Operating Temperature Range-25°C to +55°C
Protection FunctionsDifferential protection, distance protection, overcurrent protection
OutputsBinary outputs
EnclosureIP54
Mounting19" rack mounting

Related product manuals