Turbine cleaning during operation
5.3
Page 63
April 2015 HZTL2412_EN Revision E
Recommended operating state for turbine wet cleaning
The following operating state has been tested and is approved by ABB
Turbo Systems:
Characteristic / component
Conditions
short
water injection time
long
water injection time
Engine load (guide value) 20 40 %
Turbine inlet temperature
T
TE
before water injection
350400 °C
350430 °C
Water supply ensured
Water pressure
(overpressure over
atmosphere) p
WT
2.0 bar
1.5 bar
If necessary, engine performance must be reduced to maintain these
conditions.
The cleaning cycle can now be started based on the following description.
© Copyright 2015 ABB. All rights reserved.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB TPS F Series and is the answer not in the manual?

ABB TPS F Series Specifications

General IconGeneral
BrandABB
ModelTPS F Series
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals