37
If the battery cubicle is used in connection with the
PROTECT 1.1.50 or PROTECT 1.200, the strain relief is
implemented with clamps.
The battery system can now be activated. To do this, insert the
two fuses .
As the last step, fasten each cover that was initially removed.
Fig.: PROTECT 1.BP20 in connection with the PROTECT 1.100
i
PROTECT 1.100 & 1.BP20: When connecting the
battery connection cable, make sure that the plugs
are inserted quickly and firmly in the batter
y
connectors.
Prepare further PROTECT 1.BP20 battery cubicles as
described above and then connect them to the terminals (X2
and X3) of the previously installed battery cubicle with the
enclosed battery connection cables. Observe the correct
polarity "+" and "-" as well as an earth-fault- and short-circuit-
proof routing during connection.
5.5 Mechanical Blocking of PROTECT 1.
After completing the connection work, fasten the connection
terminal cover again. At the final installation site, block the
cubicles against slipping.