c
Junction box for RS485 connection and AC connection
d
AC connection
e
DC Switch(optional)
Anyhome Series(Doulble MPPT Trackers): HNSxxxxTL(xxxx=3000,3600,4000,5000,6000,7000,8000)
Object
Description
a
DC connectors ( + ) for connecting the PV strings
b
DC connectors ( ) for connecting the PV strings
c
Junction box for RS485 connection and AC connection
d
AC connection
e
DC Switch(optional)
5.2 Connection to the Public Grid (AC)
5.2.1 Conditions for Connection
CAUTION!
Unit Disconnection From Load
Disconnect the circuit breakers and switches of inverters AC and DC sides.
5.2.2 Connection to Public Grid (AC)
Measure the grid voltageto make sure within the permissible range. Disconnect the circuit breaker
between the inverter and the grid.