COMMISSIONING CHECKS
Commissioning Checks
Refer to pump manual for pump commissioning
Turn on power to controller
Turn shower on low flow and confirm pump
operates after start delay (default 5 secs.)
Run for 2-3 mins
Set shower to maximum flow
Follow the calibration setting, adjust pump speed on
controller to match maximum shower flow
Adjust RUN-ON and repeat until tray is cleared and
pump stops with minimum RUN-ON
Switch shower OFF.
Pump will RUN-ON
If you experience problems see