Installation
Hoisting and in stalling the pole
P31--2001EN/03
4/6
01--2011
© ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be
relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is
provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is
strictly prohibited.
GRID
Installing the po le
Instructions
The following table gives the steps for installing the pole before tightening
the frame :
Step
Action
1
Place the pole on the frame, install the two cross members (1),
and the fasteners (2).
Do not tighten the fasteners (2).
x4
2
1
2
2
1
H M16--75
2
18 daNm
While leaving the pole slung, tighten all of the frame fasteners to
the indicated torque.
Fasten the reinforcements (4) and (5).
Fasten the two cabinet supports (6) (if option validated).
6
4
5