4.1 - Pre-Commissioning Steps
Review “Installation” on page 15, and verify that all
steps have been completed. Conduct a visual
inspection of the installed M32 flywheel(s), paying
particular attention to the following:
Each M32 flywheel is properly secured to its
Capsule.
All electrical and communications connections to
the M32 flywheel(s) have been completed in
accordance with the instructions in this manual.
There is no debris in the Capsule(s).
Station power and network communications are
available to the M32 flywheel(s).
WARNING: DO NOT ENERGIZE THE DC
BUS AT THIS TIME.