q 10. Place the Symmetra
TM
into Bypass mode by follow-
ing the screen sequence in figure 5-24.
Fig 5-24 Initiate Bypass Mode
The Bypass LED indicator should glow, and the PowerView
display will indicate that the UPS (Symmetra
TM
) IS BY-
PASSED.
q 11. Return the Symmetra
TM
to the On-Line mode of op-
eration by following the screen sequence in figure 5-25.
Fig 5-25 Return to On-Line Mode
The Bypass LED indicator should cease to glow, and the mes-
sage UPS IS OUT OF BYPASS will appear on the PowerView
display. Press any key to return to the startup screen.
q 12. Power down the load equipment by following the
screen sequence in figure 5-26.
Fig 5-26 Power Down the Load Sequence
From the Control menu, power down the load equipment by
executing the UPS LOAD OFF command. After several sec-
onds, the UPS LOAD IS OFF message is displayed. All LED
indicators on the PowerView should be off.
q 13. Power down the Symmetra
TM
by switching the sys-
tem enable switch and the input circuit breaker to the stand
by position. The installation procedure has now been com-
pleted.
Note: This procedure is an installation checklist. Read and
follow the steps in Chapter 7 to configure the Symmetra
TM
Power
Array for your specific power needs.