EasyManua.ls Logo

Artillery GENIUS - Step 5: Pre-heating and Bed Leveling

Artillery GENIUS
114 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
07
Step 5
Now you can connect your power and turn on the machine. On the
touch screen, go to Tools -> Heat to pre-heat the nozzle and bed. Wait
till both heated up to target temperature and wait for 1 minute to allow
all components to equalize in temperature, then go to Tools -> Level.
Move the nozzle to all four corners, adjust the height by turning the
knob below the bed. Slide an A4 paper between the nozzle and the
bed, adjust the height so that the piece of paper slides, with just a bit of
drag, in all locations of the bed.
You may need to do the same process twice because an adjustment in
one corner will aect others.