15.2 Checking ue integrity
Theintegrityoftheuesystemandperformanceoftheboilercanbecheckedviatheueturretsample
points shown in diagram 15.2.a.
The case must be on the boiler and the boiler made to run at maximum output.
- Press both + buttons for 6 seconds (this will only give full CH output);
- Whentheamesymbolappearsinthedisplaypressboth+buttonsagainfor6seconds;
- The display shows the supply water temperature ( appears in the display)
The boiler will switch to maximum power output of the boiler
- Press 1x the eco- button;
The display shows XX% (heating capacity)
- Insert the analyser probe into the air intake sample point 'B'.
- Ensuretheprobereachesintotheowofairinairintakesamplepoint.Ensurethesealingconeonthe
probe is sealed to the sample point and correctly position the end of the probe.
- Allow the readings to stabilise and check that:
- O
2
isequalto,orgreaterthan20.6%.
- CO
2
islessthan0.2%
- Ifthereadingsareoutsidetheselimitsthenthisindicatesthatthereisaproblemwiththeuesystemor
combustion circuit, e.g. missing or dislodged seals.
End of measuring:
- Press the ESC button (
button).
Thedeviceswitcheso.
The display shows for 2 seconds code 180 or 181.
This completes the procedure.
A–Fluegassamplepoint
B–Airintakesamplepoint
Figure 15.2.a
A
6 sec.
°C
%
B