WE HOPE YOU WILL BE SATISFIED WITH OUR PROD-
UCT, AND WE RECOMMENED TO COMPLY WITH
THESE MAIN REGULATIONS NECESSARY FOR
LONG SERVICE LIFE AND CORRECT FUNCTION OF
THE BOILER
1. Assembly, firing-up test and operator‘s training must be carried out by an installation compa-
ny trained by the manufacturer; this company also fills in a boiler installation report (p.41).
2. During the gasification process, wood tar and condensates (acids) form in the fuel storage tank.
Therefore, there must be a Laddomat 22 or a thermoregulatory valve installed behind the boiler in
order to keep the minimal temperature of water returning to the boiler at 65 °C.
Operating temperature of water in the boiler must be in the 80 - 90 °C range.
3. Every circulating pump in the system must be regulated by an individual thermostat in order to
keep the specified minimum temperature of water returning to the boiler.
4. The boiler must not be permanently operated in an output lower than 50 %.
5. The boiler operates environmentally-friendly at the nominal output level.
6. When operating the boiler in a lower output mode (summer operation or heating up warm ser-
vice water), it is necessary to fire-up daily.
7. We therefore recommend installing the boiler with accumulating storage tanks and Laddomat 22,
which provides 20 - 30 % fuel consumption decrease, and longer service life of both – the
boiler and the chimney and user-friendlier operation.
8. If you cannot install the boiler into an accumulation system, then we recommend installing it at
least with one equalising tank; the volume of which should be 25 l per 1 kW of the boiler output.
9. Use only dry fuel with 12 - 20 % moisture content – higher moisture content decreases the
boiler’s performance and increases consumption.
Boilers with an extraction ventilator are marked with S (DC 70S excluded) at the end of the
label.
CAUTION – if the boiler is installed with a Laddomat 22 or with a TV 60/65/70/75 °C
and with the accumulation tanks (see attached schematics), the guarantee period for
the boiler drum is extended from 24 to 36 months. The guarantee period for other
parts remains unaffected. In non-compliance with these instructions the drum’s and
the heatproof pipes’ service life may dramatically decrease. The boiler drum may cor-
rode in as little time as 2 years.
CAUTION - INSTALLER SHOULD ALWAYS COMPLY WITH LOCAL PLANNING
AND BUILDING REQUIREMENTS.