MAINTENANCE PROCEDURE
Checks and adjustments
ADIABATIC PRE-COOLER WATER FLOW
A minimum water flow must be distributed over the adiabatic pre-cooler as per minimum water flow rates. (See
table below "Minimum recommended adiabatic pre-cooler water flow rates").
The water flow will depend on the supply water pressure, and can be set with the 2 concentric hex screws on the
water flow valve on the flow meter. First open the plastic cover plate of the water flow adjustment screw.
Water flow adjustment screw
Model Number of
fans
Recommended pre-cooler water flow per unit
Once Through
Recirculation
Make-up Pump
TVFC-EC-8022-* 4 fans 14 l/min 14 l/min 40 l/min
TVFC-EC-8023-* 6 fans 22 l/min 22 l/min 60 l/min
TVFC-EC-8024-* 8 fans 28 l/min 28 l/min 80 l/min
TVFC-EC-8025-* 10 fans 36 l/min 36 l/min 86 l/min
TVFC-EC-8026-* 12 fans 44 l/min 44 l/min 104 l/min
TVFC-EC-8027-* 14 fans 50 l/min 50 l/min 121 l/min
Recommended adiabatic pre-cooler water flow rates