Commissioning
Compact manual b maXX
®
BM4400, BM4600, BM4700
Document no.: 5.06014.02
43
of 94
6
6.5 Executing commissioning
Start with the commissioning, after you have completed the preparations.
1 Effectuate the power supply to the b maXX
®
(supply voltage + control voltage).
Hereupon the device starts up and shows its operational readiness by flashing of the
orange-colored LED H-2 (Power ON).
m LED H-2 must light up orange, this means Power ON, the device is ready-to-oper-
ate.
m LED H-2 may not light up green: The green shining LED H-2 signified ’operation en-
abled’! The motor is power supplied and can rotate! Immediately cancel this with the
switch element pulse enable or quickstop enable!
m LED H-3; the red luminous LED means current limit reached. Reduce the load of the
motor. Continue the parameterization.
m LED H-4; a red flashing LED signifies a state of error. Later the error is removed with
the help of the operating program WinBASS II / ProDrive. Continue the parameter
-
ization.
2Now plug on the (RS232-)cable connector from the PC/laptop to the controller at the
bmaXX
®
.
The communication between the processor and the b maXX
®
runs through the con-
nection cable.
3 Start WinBASS II (up to FW 3.09) or ProDrive (from FW 3.07), as far as it isn’t running
yet.
NOTE
In case you get an error message referring a plug-in module, then please first check if the
plug-in module is accurately cabled and if need be, is supplied with voltage.