XPR-10 Series Two-Post Lifts 33 P/N 5900951Rev. D May 2019
To install the Posts:
1. Using a Forklift or Shop Crane, move the Posts to the Chalk Line Guides you created earlier.
2. Stand up each Post, one at a time, and move it to the appropriate location relative to the Chalk
Line Guides.
3. Double check your measurements against the Specifications for your Lift model:
Distance from back of one Base Plate to back of the other Base Plate: Width Overall value
Distance from inside of one Post to inside of the other Post: Inside Posts value
4. Using the Base Plates as guides, drill each hole 5 inches deep.
Do not drill all the way through the Concrete; if you punch completely through the slab, you could
compromise the holding strength of the Anchor Bolt once put into place.
Go in straight; do not let the drill wobble.
Use a carbide bit (conforming to ANSI B212.15-1994).
The diameter of the drill bit must be the same as the diameter of the Anchor Bolt. So if you are
using a ¾ inch diameter Anchor Bolt, for example, use a ¾ inch diameter drill bit.
5. Vacuum each hole clean.
BendPak recommends using a vacuum to get the hole very clean. You can also use a wire brush,
hand pump, or compressed air; just
make sure to thoroughly clean each hole
.
Do
not
ream the hole. Do
not
make the hole any wider than the drill bit made it.