EasyManua.ls Logo

Biodom 33 - Installation; Placement

Biodom 33
61 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Biodom 33
Biodom 33Biodom 33
Biodom 33
|
| |
| instructions for use, maintenance and installation | version 1.0 July 2017
7
existence and suitability of flue pipe cover resistance;
possibility of outside air intake;
possibility of simultaneous use of generator for connection with other equipment.
If the results of all above provided checks are positive, installation may proceed. Carefully heed to
instructions provided by the manufacturer, as well as safety and fire prevention standards in force.
After the first start-up of the boiler, perform a minimum 30-minute test of operation to check all
required demands.
When the installation is complete, the installer must provide the customer with the following:
instructions for use, maintenance and installation from the manufacturer (if not included in
the unit);
required documentation in accordance with standards in force;
perform training of customer for operation and regular maintenance and cleaning of the
device.
3. INSTALLATION
Responsibility for installation work in the space is entirely upon the customer.
Before proceeding with installation, the installer must comply with all required legal safety standards,
especially:
Check that norms regarding pellet boiler installation meet local, national and European
norms
Heed to requirements set forth in this document
Check that pipes and air intake are compliant with the type of installation
Do not make temporary electrical connections by using unsuitable cables
Check earthing of electrical system
Always use individual safety equipment and all legally required protection
Always allow sufficient space for maintenance work
Acquire consent of chimney sweep for connection of boiler to flue
Perform measurement of smoke gases outlet after finished installation.
3.1. PLACEMENT
It is advisable to remove pellet boiler packaging only when it is in the place of installation.
If the adjacent walls and/or flooring are made of material that is not heat resistant, suitable
protection must be provided using insulating, non-combustible material.
For protection of flooring, made of flammable material, we advise installing a metal plate with
thickness 3 to 4 mm under the boiler, which protrudes at least 30 cm out from the front of the pellet
boiler.
Pellet boiler must be installed in accordance with drawing that defines distances from walls (figure 1).

Related product manuals