9. Operation
The unit will turn on as soon as the power supply is activated.
Pump priming
If the system pressure is below 0.8 bar the pump will prime itself. Above a
system pressure of 0.8 bar please perform the following steps:
1.isolate the system
2.loosen the flex hose
Manually run each pump by performing the pump test described in chapter 9.2 Normal operation.
9.1. Commissioning
The unit will guide you through the commissioning process.
Press to continue
Set „Safety relief valve“ setting by pressing the or button. Accept the setting by
pressing the button.
Set Pressure set point“ setting by pressing the or button. Accept the setting by
pressing the button.
After the commissioning is completed the settings will be stored on the device persistently. To
reset the unit please read chapter 9.5 Resetting.