8. Important hints
8.1 First start-up
First start-up of the machine has to be Attention:
carried out by the BÖWE service organization. Before opening the control
box or removing panelling,
turn main switch to "0".
8.1.1 Filling the machine with solvent
(emission-free filling is standard)
Only use stabilized, neat TETRACHLOROETHANE Attention:
(Perc) in accordance with DIN 53978. Before turning on the
pump must be filled with solvent.
Required solvent amount for the first filling:
P 240 /P 300 USA: 220 l (360 kg) 58.1 USgal (794 lb)
P 300 /P 350 USA: 260 l (420 kg) 68.7 USgal (926 lb)
The emission-free filling takes place in a closed system:
- Screw off pump line cap Attention:
- Connect hose between barrel (bottom) and Perc has a high
pump suction side liposolubility. When using
perc wear gloves and
- Connect hos (gas displacement line) subsequently put on
between barrel and water separator cream on hands. No
smoking. If perc gets
- Open ball valve into the eyes seek further
medical advice.
- Start program P37
- Tanks fill up overflowing one into the other
- Once the tanks are full, stop program P37
- Close ball valve
- Remove hose connection from barrel
- Screw cap back on pump pipe
!
!