3.1 INSTALLATION GUIDELINES
l Pressure - Temperature Diagram
Please be aware of the pressure-temperature dependence according to the
respective fitting material as shown in the diagram below.
bar
PVDF/PP/PVC/Brass/SSt
PVDF/PP/PVC/Brass/SSt
T°C
l The device must be protected against constant heat radiation and other
environmental influences such as magnetic fields or direct exposure to
sunlight.
l Ensure that the device is not located near any large machinery which
may interfere with the transmitter as this can have an effect on the
measurement readings.
In order to ensure a high precision of the measure and good stability of
the zero point, the transmitter must be installed into the processed
medium at least 24 H before calibration (electrode passivation).
Dismounting precautions:
All precautions must be taken before removing the transmitter depending
on the process used as the pipe may contain dangerous / agressive hot
fluids.