39
rate (80%).
Adjust staging of boilers
Description
Electrical Connection(s)
Programming Instructions
Upon a call for heat the lead
boiler will fire up to the
specified base load rate
(80%). If the temperature is
not within Error threshold
(5
o
F) of setpoint after
Interstage delay (2 minutes) a
lag boiler will be brought
online and will also fire up to
the base load rate specified.
This method will then be
repeated for the next lag
boiler, if available.
1) Press
and
2) Press [Lead Lag Master Configuration]
3) Press [Advanced Settings >]
4) Press the to arrive at Add Stage
5) Select Error threshold
6) Select Interstage delay