2.2.1 - Moving
See chapter 1.1 “Installation safety considerations”.
2.2.2 - Siting the unit
Always refer to the chapter “Dimensions and clearances” 
to confirm that there is adequate space for all connections 
and service operations. For the centre of gravity coordinates, 
the position of the unit mounting holes, and the weight dis-
tribution points, refer to the certified dimensional drawing 
supplied with the unit.
Typical applications of these units are in refrigeration 
systems, and they do not require earthquake resistance. 
Earthquake resistance has not been verified.
CAUTION: Only use slings at the designated lifting 
points which are marked on the unit.
Before siting the unit check that:
•  the permitted loading at the site is adequate or that 
appropriate strenghtening measures have been taken.
•  the unit is installed level on an even surface (maximum 
tolerance is 5 mm in both axes).
•  there is adequate space above the unit for air flow and 
to ensure access to the components.
•  the number of support points is adequate and that 
they are in the right places.
•  the location is not subject to flooding. 
•  for outdoor installations, where heavy snowfall is likely 
and long periods of sub-zero temperatures are normal, 
provision has to be made to prevent snow accumulating 
by raising the unit above the height of drifts normally 
experienced. Baffles may be necessary to deflect strong 
winds. They must not restrict air flow into the unit.
CAUTION: Before lifting the unit, check that all casing 
panels are securely fixed in place. Lift and set down the 
unit  with great care. Tilting and jarring can damage the 
unit and impair unit operation.
If 30GX units are hoisted with rigging, it is advisable to 
protect coils against crushing while a unit is being moved. 
Use struts or spreader bars to spread the slings above the 
unit. Do not tilt a unit more than 15°.
WARNING: Never push or lever on any of the enclosure 
panels of the unit. Only the base of the unit frame is 
designed to withstand such stresses.
Checks before system start-up
Before the start-up of the refrigeration system, the complete 
installation, including the refrigeration system must be 
verified against the installation drawings, dimensional 
drawings, system piping and instrumentation diagrams and 
the wiring diagrams.
During the installation test national regulations must be 
followed. If no national regulation exists, paragraph 9-5 of 
standard EN 378-2 can be used as a guide.
External visual installation checks:
•  Compare the complete installation with the refrigera-
tion system and power circuit diagrams.
•  Check that all components comply with the design 
specifications.
•  Check that all safety documents and equipments that 
are required by current European standards are 
present.
•  Verify that all safety and environmental protection 
devices and arrangements are in place and comply 
with the current European standard.
•  Verify that all relevant documents for pressure vessels 
(certificates, name plates, files, instruction manuals etc.) 
required by the current European standards are present.
•  Verify the free passage of access and safety routes.
•  Check that ventilation in the plant room is adequate.
•  Check that refrigerant detectors are present.
•  Verify the instructions and directives to prevent the 
deliberate removal of refrigerant gases that are harmful 
to the environment.
•  Verify the installation of connections.
•  Verify the supports and fixing elements (materials, 
routing and connection).
•  Verify the quality of welds and other joints.
•  Check the protection against mechanical damage.
•  Check the protection against heat.
•  Check the protection of moving parts.
•  Verify the accessibility for maintenance or repair and 
to check the piping.
•  Verify the status of the valves.
•  Verify the quality of the thermal insulation and of the 
vapour barriers.