Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53420028-01 Printed in U.S.A. Form No. 42B-6SI Pg CL-1 1-24 Replaces: 42B-5SI
INITIAL START-UP CHECKLIST
FOR AIRSTREAM™ 42BHE,BVE06-40 SYSTEM FAN COIL AIR CONDITIONERS
(Remove and use for job file.)
START-UP CHECKLIST
The following is a checklist to be completed before start-up:
1. General visual unit and system inspection Yes No
2. Check that unit is level Yes No
3. Record electrical supply voltage Yes No
4. Check all wiring for secure connections Yes No
5. Verify with straight edge alignment of motor and blower pulleys Yes No
6. Tighten all set screws Yes No
7. Confirm V-belt is properly tightened Yes No
8. Check condensate drain connection Yes No
9. Verify trap is deep enough Yes No
10. Prime the trap with water Yes No
11. Check supply and return water connections for leaks Yes No
12. Fill systems with water by opening supply ball valve and control valve Yes No
13. Open air vent on top of coil to vent air out of system Yes No
14. Open return ball valve Yes No
15. Engage power only long enough to verify proper blower rotation Yes No
16. Check all ductwork and grilles in place Yes No
17. Check all unit panels and filters in place Yes No
18. Start fans, pumps, chillers, etc. Yes No
19. Check for overload conditions of all units Yes No
20. Check all ductwork and units for air leaks Yes No
21. Balance water systems, as required Yes No
22. Balance air systems, as required Yes No
23. Record all final settings for future use Yes No
24. Check piping and ductwork for noise or vibration Yes No
25 Check all dampers for proper operation Yes No
26. Verify proper cooling operation Yes No
27. Verify proper heating operation Yes No
28. Reinstall all covers and access panels Yes No
29. Verify proper condensate drainage Yes No
NOTE: To avoid injury to personnel and damage to equipment or prop-
erty when completing the procedures listed in this start-up checklist,
use good judgment, follow safe practices, and adhere to the safety
considerations/information as outlined in preceding sections of this
Installation, Start-Up, and Service document.