URBAN DC
23
Installation Guide
Verification
1 POWER INPUT
Before proceeding, make sure voltage is present in the terminal blocks.
Pay special attention to Neutral Cable.
2 MAINTENANCE MODE
Pull outward the Tamper Switch located in the lower half of the Charge Point.
3 CAREFUL WITH THE WIRES
Before closing the unit, keep in mind that all cables should remain inside.
4 CHECK THE PLUGS
Plugs should be in good conditions before starting the unit.
5 ELECTRICAL PROTECTIONS
If the unit includes electrical protections, rearm all of them.
6 CHECK THE BEACON INDICATOR
The beacon indicator should light properly. Here’s the reference:
7 OPERATION
Check no abnormal noise appears while the unit is charging.
8 PREVENTIVE MAINTENANCE
It is recommended to perform one preventive maintenance per year.
PLUG STATE
Available
Charging
Fault
BEACON COLOR
Green
Blue
Red
H