Cisco UCS C200 Server Installation and Service Guide
OL-20732-02
Chapter 2      Installing the Server
  Preparing for Installation
Preparing for Installation 
This section includes the following topics:
  • Installation Guidelines, page 2-3
  • Rack Requirements, page 2-4
  • Required Equipment, page 2-4
Installation Guidelines 
Warning
To prevent the system from overheating, do not operate it in an area that exceeds the maximum 
recommended ambient temperature of: 35° C (95° F).
 
Statement 1047
Warning
The plug-socket combination must be accessible at all times, because it serves as the main 
disconnecting device.
 
Statement 1019
Warning
This product relies on the building’s installation for short-circuit (overcurrent) protection. Ensure that 
the protective device is rated not greater than: 250 V, 15 A.
 
Statement 1005
Warning
Installation of the equipment must comply with local and national electrical codes.
 
Statement 1074
When installing the server, follow these guidelines:
  • Plan your site configuration and prepare the site before installing the server. See the Cisco UCS Site 
Preparation Guide for the recommended site planning tasks.
  • Ensure that there is adequate space around the server to allow for servicing and for adequate airflow. 
The airflow in this server is from front to back.
  • Ensure that the air-conditioning meets the thermal requirements listed in Appendix A, “Technical 
Specifications.”
  • Ensure that the cabinet or rack meets the requirements listed in the “Rack Requirements” section on 
page 2-4.
  • Ensure that the site power meets the power requirements listed in Appendix A, “Technical 
Specifications.” If available, you can use an uninterruptible power supply (UPS) to protect against 
power failures. 
Caution Avoid UPS types that use ferroresonant technology. These UPS types can become unstable with systems 
such as the Cisco UCS, which can have substantial current draw fluctuations from fluctuating data traffic 
patterns.