Airflow Requirements
When planning your site for installing vEdge routers, allow enough clearance around the installed router.
Since the routers work with a front-to-back airflow there are no clearance requirements for the sides, but it is
recommended that you provide at least 3 in. of clearance at the back.
Install the vEdge 100 Router
Once you have prepared your site for router installation, unpack the vEdge 100 router and mount it either on
the wall or in a 19-inch rack.
Unpack the vEdge 100 Router
A vEdge 100 router is shipped in a cardboard carton and secured firmly in place with foam packing material.
The carton contains a packing list and Quick Start instructions. It is recommended that you do not unpack the
router till you are ready to install it.
To unpack the router:
1. Open the top flaps of the carton.
2. Gradually remove the packing foam holding the router and the accessories in place. See Figure 1.
3. Take out the router and each accessory.
4. Verify the router components against the packing list included in the box (see packing list below).
Figure 1: Unpacking the vEdge 100 Router
Hardware Installation Guide for vEdge Routers
10
vEdge 100 Router
Install the vEdge 100 Router

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Cisco vEdge 100m and is the answer not in the manual?

Cisco vEdge 100m Specifications

General IconGeneral
BrandCisco
ModelvEdge 100m
CategoryNetwork Router
LanguageEnglish

Related product manuals