Connecting the Pipework
1. Make sure that your work area (including the vice, workbench, tool storage
area, and floor) is totally clean of particles or previous work. Cleanliness
and correct assembly practice can avoid most seal problems.
2. Make sure that the gas outlet pipes are properly supported before
connection.
Electrical Installation
CNG Cable Requirements
Cable requirements are as follows:
3 Core Steel Wire Armour Cable 2.5mm
2
,
220 - 240 Volts. 50 Hz, +/-10%
Core 1: 230 Volt Supply (Active).
Core 2: Neutral.
Core 3: Earth.
25w Idle, 200W with all solenoids active.
Make sure that there is at least a two metre cable tail on both
the incoming underground 230 V cables to reach the C4000 flameproof box.