Scheduled Servicing
Servicing
Compac Industries Ltd.
Page 24
www.compacngv.com
Scheduled Servicing
Weekly checks
Check the sealing and operation of the three-way refuelling valve (see page 26).
Check the sealing and operation of the solenoids. Refer to: Checking the Sealing of the Solenoid (see page 25)
Suggested 6-monthly service
Check the post for leaks (see page 25).
Check hoses for damage and electrical continuity
Replace breakaway seals
Replace 3-way refuelling valve seals and inspect ball for scratches and wear. Replace ball if necessary.
Replace nozzle O-rings. Check that the nozzle is not damaged or bent, replace if necessary
OEM Nozzles and Breakaways - Refer to manufacturer’s instructions
Suggested yearly service
In addition to all the checks listed in the 6-month service, carry out the following:
Dismantle and clean the solenoid valves. Replace the seals and O-rings (see page 27).
Check the loading post calibration. Meter Calibration (see page 40).
Check the C4000 Processor Board is clean, dry and dust free.
Check the C4000 flameproof box lid is bolted down tight and all glands are tight.

Other manuals for Compac CNG

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Compac CNG and is the answer not in the manual?

Compac CNG Specifications

General IconGeneral
BrandCompac
ModelCNG
CategoryDispenser
LanguageEnglish

Related product manuals