5.6 Commissioning checklist
Commissioning checklist/Check off measures carried out
Chapter
1. Supply indoor unit and outdoor unit (if present) with voltage These instructions Chap. 3.7
2. Enter "Expert code" RoCon+ 4.5.1
3. Set the operating parameters
[→Configuration Wizard →Setting parameters]
[Hot water temperature target 1]
▪ Do not set below 40°C during commissioning.
▪ Never set below 35°C after commissioning!
RoCon+ 5.2
4. Activate the ventilation function RoCon+ 4.5.7
▪ Check the water pressure
These instructions Chap. 5.3
▪ Checking the minimum flow
Chap. 5.4
5. Activate the "Heating" operating mode
Observe the waiting time (up to 5min)
Observe Chap. 5.2 at low ambient temperatures.
RoCon+ 4.1
6.
Commissioning is complete when a DHW temperature of more than
40°C appears on the display.
7. [Screed drying] (if necessary)
Screed drying only after commissioning is complete. As soon as the temperat-
ure of the storage tank is at least 40°C, activate (also possible without outdoor
unit).
RoCon+ 4.5.7
5.7 Handover to the operating
company
Once the test run is finished and the unit operates properly, please
make sure the following is clear for the user:
▪ Fill in the installer setting table (in the operation manual) with the
actual settings.
▪ Make sure that the user has the printed documentation and ask
him/her to keep it for future reference. Inform the user that he can
find the complete documentation on the url as earlier described in
this manual.
▪ Explain the user how to properly operate the system and what he/
she has to do in case of problems.
▪ Show the user what he/she has to do in relation to maintaining the
unit.
▪ Explain the user about energy saving tips as described in the op-
eration manual.